You’ve done the work. The data is collected, the root cause is confirmed, the fix is in. Now you have fifteen minutes with the sponsor and three managers who haven’t followed the project. How do you tell the story so they understand it and agree to the next step? A Six Sigma project storyboard is the standard answer. It lays out the project as a sequence of panels, one per phase, mostly charts and short captions. ASQ lists storyboards at Green Belt, and many certification projects end with one.

Six Sigma project storyboard layout with one panel per DMAIC phase: Define, Measure, Analyze, Improve and Control

What is a Six Sigma project storyboard?

A storyboard is a visual summary of a project, organized by DMAIC phase. It shows what the team did, what it found and what it decided, in the order it happened.

Formats vary:

  • a single large poster, common for project fairs and wall displays
  • a short slide deck, one or two slides per phase
  • a one-page summary, similar to an A3 report

The idea comes from film. Directors and animators sketch scenes in order before shooting, so everyone can see how the story flows. A project storyboard does the same for a team’s work. Anyone can follow it from problem to result without reading a long report.

Why storyboards work

  • They’re visual. Charts show baselines, root causes and results faster than paragraphs.
  • They follow a logic. DMAIC is a story: problem, evidence, cause, solution, sustain.
  • They build as you go. Add each phase’s panel at the end of that phase. By the final review, it’s done.
  • They support phase reviews. A tollgate review walks through the panels for the current phase and checks they’re complete.
  • They share learning. Other teams can see what worked.

What goes in each panel

Define

  • Problem statement in one or two sentences
  • Goal statement with a measurable target and date
  • Scope (in and out), often as a SIPOC
  • Team and sponsor
  • Business case: why it matters

Measure

  • The primary metric and how it’s defined
  • Measurement system result (a passed Gage R&R or attribute agreement)
  • Baseline chart (run chart or control chart)
  • Baseline capability or sigma level, if relevant

Analyze

  • The cause-and-effect diagram or C&E matrix, with suspects highlighted
  • The key evidence: Pareto, scatter, hypothesis test result, multi-vari
  • A one-line statement of confirmed root causes

Improve

  • Solutions considered and how they were chosen
  • Pilot plan and pilot results
  • Before-and-after comparison on the primary metric

Control

  • The control plan summary
  • Control chart showing the new level holding
  • Who owns the process now
  • Financial results, validated if possible
  • Lessons learned and next steps

Worked example: a call center hold time storyboard

Here’s what each panel might say for a project to reduce customer hold times (an illustrative project).

Define panel.

  • Problem: customers calling the billing line wait too long before reaching an agent. Complaints about hold time have risen.
  • Goal: cut average hold time on the billing line by half within five months.
  • Scope: billing line, weekday hours. Technical support line out of scope.
  • Visual: a SIPOC and a small chart of monthly hold-time complaints.

Measure panel.

  • Metric: hold time from end of menu to agent answer, from the phone system log.
  • MSA: confirmed log timestamps match manual stopwatch checks on a sample of calls.
  • Visual: an individuals control chart of daily average hold time. It’s stable but high, with a weekly pattern.

Analyze panel.

  • Visual 1: a fishbone with staffing, call routing, menu design and call length branches.
  • Visual 2: stratified chart showing hold time spikes on Monday mornings and after bills are mailed.
  • Visual 3: a Pareto of call reasons. “Explain my bill” is the top reason.
  • Root cause statement: staffing doesn’t follow demand peaks, and many calls ask questions the bill could answer.

Improve panel.

  • Solutions: shift schedules aligned to the demand pattern; a clearer bill layout with a “what changed” box; a callback option at peak times.
  • Pilot: new schedules and callback for four weeks.
  • Visual: before-and-after box plots of hold time. A two-sample test confirms the reduction.

Control panel.

  • Control plan: weekly review of forecast vs. actual calls; schedule adjusted monthly.
  • Visual: control chart showing the new lower level holding over two months.
  • Owner: call center operations manager.
  • Results: hold time near the goal; complaints down. Savings in overtime reviewed with finance.
  • Next step: the bill redesign goes to the billing team as a separate project.

Scrap reduction poster

A plant’s scrap reduction storyboard fits on one poster by the line. Define shows the scrap cost trend. Measure shows a Gage R&R summary and a p-chart of scrap rate. Analyze shows a Pareto of scrap reasons and a scatter of mold temperature against short shots. Improve shows the new temperature control and a before-and-after p-chart. Control shows the operator check sheet and the ongoing chart. Operators walking past can see the project and its results every day.

The spreadsheet behind the board

ASQ pairs storyboards with a second presentation tool: a spreadsheet summary of results. The board tells the story. The spreadsheet holds the numbers a reviewer or finance partner will want to check. Keep one row per metric, with the operational definition, data source, baseline, target, current value, date of the last update and owner. Add rows for costs and validated savings. The same sheet becomes the project record at closure, so the data and inputs that document the project live in one place instead of in a dozen chart files.

Tips for a strong Six Sigma project storyboard

  • One message per panel. Write a headline that states the finding. “Monday mornings drive most of the long holds” beats “Analysis results.”
  • Charts over text. If a chart can show it, don’t write it.
  • Label everything. Axes, units, dates and data source.
  • Show the baseline next to the result. The before-and-after comparison is the center of the story.
  • Be honest about what didn’t work. Discarded solutions and surprises add credibility.
  • Keep it current. Update the board at each phase, not just at the end.
  • Use plain language. The audience may not know what a p-value is. Say what it means.

Common storyboard mistakes

  • The data dump. Every chart the team made, all on the board. Pick the two or three that carry the argument for each phase and keep the rest in an appendix.
  • No baseline. A result chart with nothing to compare it against doesn’t show improvement.
  • Solution first. Some boards jump from the problem to the fix, skipping Analyze. Reviewers then ask, fairly, how the team knows the fix addresses the cause.
  • Jargon headlines. “Reject H0, p < 0.05” means little to most sponsors. “Monday staffing explains most of the difference” says the same thing in their language.
  • Stale boards. A poster still showing last month’s Measure panel tells the floor the project has stalled, even if it hasn’t.

Storyboards and phase reviews

At each phase review (tollgate), the sponsor checks that the phase is complete before the team moves on. The storyboard panel for that phase is the evidence. A missing MSA result or an unconfirmed root cause shows up as a gap on the board. Our guides to the Define phase and project closure cover what each review should confirm.

On the exam: Six Sigma project storyboard

ASQ lists storyboards at Green Belt. Expect:

  • Purpose. A visual summary of the project, organized by phase, used to communicate progress and results.
  • Contents. Key charts and findings from each DMAIC phase, backed by a spreadsheet summary of results.
  • Use. Phase reviews, project presentations, sharing lessons learned.
  • Comparison. Storyboards emphasize visuals and flow over detailed written reports.

If a question asks for the best way to communicate a project’s progress to stakeholders at a review, a storyboard is usually the intended answer.

When you’re ready, there are a few ways I can help:

First, join 12,000+ other Six Sigma professionals by subscribing to my email newsletter. A short read every Monday to start your work week off correctly. Always free.

* * *

If you’re looking to pass your Six Sigma Yellow Belt, Green Belt or Black Belt exam, I’d recommend starting with my affordable study guide:

1)β†’ 🟑Pass Your Six Sigma Yellow Belt: built for ASQ, IASSC and ILSSI, 1,700+ practice questions with explanations, and six full-length mock exams for your exam

2)β†’ 🟒Pass Your Six Sigma Green Belt: a study guide organized by the exam Body of Knowledge, 1,300+ practice questions with detailed answer explanations, and 20 full-length mock exams

3)β†’ ⚫Pass Your Six Sigma Black Belt: the full Black Belt Body of Knowledge, 2,200+ practice questions with detailed answer explanations, and 20 full-length mock exams

You’ve spent so much effort learning Lean Six Sigma. Why leave passing your certification exam up to chance? This comprehensive study guide offers 1,700+ exam-like questions for Yellow Belts, 1,300+ for Green Belts and 2,200+ for Black Belts with full answer walkthroughs, access to instructors, detailed study material, and more.

​ Thousands have used this system to prepare. Join them here. 

Author

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.