A project status report is a short, regular summary that tells sponsors and stakeholders where a project stands: what is done, what comes next, whether it is on track, and what help the team needs. It works with two other documents. An agenda plans a meeting before it starts. Meeting minutes record what was decided and who will do what.
ASQ lists all three in section I.D.4 of the 2022 Yellow Belt body of knowledge, Communication methods, at the Apply level. You should be able to explain how teams use agendas, meeting minutes and project status reports, and how they support project success.
The three documents at a glance
| Document | When | Who reads it | What it answers |
|---|---|---|---|
| Agenda | Before the meeting | The people attending | Why are we meeting and what will we cover? |
| Meeting minutes | Right after the meeting | Attendees and anyone who missed it | What was decided, and who does what by when? |
| Project status report | On a set schedule, often weekly or every two weeks | Sponsor, champion, process owner and other stakeholders | Is the project on track, and what does the team need? |
Agendas
An agenda is the plan for a meeting. Send it at least a day ahead so people can prepare. A useful agenda lists:
- The purpose of the meeting in one line.
- The topics in order, with a time limit and an owner for each.
- Any reading or data to bring.
- The start time, end time and place.
The agenda keeps the meeting on topic and on time. When a new subject comes up, the leader can park it for later and go back to the list. Here is an agenda for a 30 minute weekly team meeting.
| Topic | Owner | Minutes |
|---|---|---|
| Review open action items | Team leader | 5 |
| Data collection results | Team member | 10 |
| Pick the top causes to test | All | 10 |
| Recap actions and next steps | Scribe | 5 |
| Total | 30 |
Meeting minutes
Minutes are the written record of a meeting. They are not a transcript. Good minutes capture:
- The date, who attended and who was absent.
- The decisions made.
- The action items: what, who and by when.
- Open issues carried to the next meeting.
Send them within a day. Without minutes, people remember different decisions, actions have no owner, and absent members fall out of the loop. The next meeting starts with the action items from the last set of minutes. For more on how teams run meetings, see team dynamics and mechanics.
Project status reports
Team meetings keep the team aligned. A status report keeps everyone else aligned. The sponsor or champion is not in the weekly meeting, but that person controls the resources and removes roadblocks. The communication plan says who gets the report, how often and in what form.
A typical report fits on one page:
- Project name, date, leader and current DMAIC phase.
- Overall status, often as a color. Green is on track, yellow is at risk, red is off track.
- Progress on the main measure against the baseline and the goal.
- Work finished since the last report.
- Work planned for the next period.
- Schedule: the next milestone or tollgate review and whether the date holds.
- Risks, issues and the help needed from the sponsor.
Worked example: a status report
A team is cutting late orders. The project charter gives a baseline of 14% late and a goal of 5%. After a pilot, the latest month is at 9%.
| Item | This period |
|---|---|
| Phase | Improve |
| Overall status | Yellow |
| Main measure | Late orders 9% (baseline 14%, goal 5%) |
| Done since last report | Pilot of the new pick list on line 2 |
| Next two weeks | Roll out to lines 1 and 3 |
| Schedule | Improve tollgate planned for August 1, now expected August 8 |
| Action items | 9 of 12 closed |
| Help needed | Approval for 2 hours of training per operator |
The numbers tell the sponsor how far along the team is. The measure has moved 14 – 9 = 5 points. The goal needs 14 – 5 = 9 points. So the team is 5 / 9 = 56% of the way there. On actions, 9 / 12 = 75% are closed.
The status is yellow, not green. The measure is not yet at the goal and the tollgate has slipped a week. The report ends with a clear ask. That is the part a sponsor can act on.
How they support project success
- Meetings are shorter and end with decisions.
- Every action has an owner and a date.
- Sponsors hear about problems early, while they are still cheap to fix.
- Stakeholders are not surprised at a tollgate.
- There is a record of what was decided and why. It feeds the final project documentation.
Common mistakes
- No agenda, or one handed out as the meeting starts.
- Minutes that record the discussion but no owners or dates.
- A status report that says only “on track.”
- A report that stays green until the week it turns red. Bad news does not get better with age.
- A report so long that the sponsor cannot find the point in a minute.
What to expect on the exam
- An agenda comes before the meeting. Its job is to let people prepare and to keep the meeting focused and on time.
- Minutes are the record of decisions and action items, with owners and due dates.
- A status report is for the sponsor and stakeholders outside the team. It covers progress, risks and help needed.
- Match the problem to the document. Nobody remembers who owns an action: minutes. The sponsor asks if the project is on track: status report. Meetings drift and run long: an agenda with time limits.
When you’re ready, there are a few ways I can help:
First, join 12,000+ other Six Sigma professionals by subscribing to my email newsletter. A short read every Monday to start your work week off correctly. Always free.
* * *
If you’re looking to pass your Six Sigma Yellow Belt, Green Belt or Black Belt exam, I’d recommend starting with my affordable study guide:
1)→ 🟡Pass Your Six Sigma Yellow Belt: built for ASQ, IASSC and ILSSI, 1,700+ practice questions with explanations, and six full-length mock exams for your exam
2)→ 🟢Pass Your Six Sigma Green Belt: a study guide organized by the exam Body of Knowledge, 1,300+ practice questions with detailed answer explanations, and 20 full-length mock exams
3)→ ⚫Pass Your Six Sigma Black Belt: the full Black Belt Body of Knowledge, 2,200+ practice questions with detailed answer explanations, and 20 full-length mock exams
You’ve spent so much effort learning Lean Six Sigma. Why leave passing your certification exam up to chance? This comprehensive study guide offers 1,700+ exam-like questions for Yellow Belts, 1,300+ for Green Belts and 2,200+ for Black Belts with full answer walkthroughs, access to instructors, detailed study material, and more.
Thousands have used this system to prepare. Join them here.