Picture a busy machine operator. They don’t have time to calculate subgroup averages and ranges every hour. They need a quick rule: keep running, adjust, or stop. A pre-control chart gives them that. It splits the specification into green, yellow and red zones and uses a few simple rules on small samples. Villanova covers PRE-control at Green and Black Belt, usually right next to regular control charts, so it helps to know how the two differ.

Pre-control chart zones for a 10.00 plus or minus 0.08 mm shaft: red, yellow and green zones with the PC lines at 9.96 and 10.04 mm

What is a pre-control chart?

PRE-control is a simple process monitoring method developed in the 1950s by consultants at Rath & Strong. It uses the specification limits, not process data, to set its zones.

The tolerance is divided like this:

  • Green zone: the middle half of the tolerance. The boundaries are called the PRE-control (PC) lines.
  • Yellow zones: between each PC line and its spec limit. Each yellow zone is one quarter of the tolerance.
  • Red zones: outside the spec limits.

If the process is centered and capable, most parts land in green, a few in yellow, and almost none in red.

The traffic light colors make the rules easy to remember on the floor. Green means go. Yellow means caution. Red means stop.

How to set up the zones

  1. Find the specification limits (LSL and USL) and the nominal target.
  2. Calculate the tolerance: USL − LSL.
  3. Set the PC lines at one quarter of the tolerance in from each spec limit. For a two-sided spec with a centered target, that’s nominal ± one quarter of the tolerance.
  4. Label the zones: green between the PC lines, yellow between the PC lines and spec limits, red outside the specs.

For a one-sided spec there’s a single PC line. The usual rule puts it halfway between the best achievable value and the spec limit; conventions vary, so follow your course text on the exam.

The PRE-control rules

There are two stages: qualifying the process at setup, and running it.

Qualification (setup)

Measure parts one at a time after setup.

  • Keep going until you get five consecutive parts in the green zone. The process is qualified. Start production.
  • If a part lands in yellow, restart the count.
  • If you get two yellows in a row, adjust the process and start qualification again.
  • If any part lands in red, stop, adjust, and start again.

Running

Once running, sample two consecutive parts (often called A and B) at regular intervals.

Result for A and BAction
Both greenContinue
One green, one yellowContinue
Both yellow, same sideAdjust the process (it has shifted)
Both yellow, opposite sidesStop and find out why variation has grown
Any redStop, adjust, and requalify

Sampling frequency

A common guideline is to take about six pairs between process adjustments or stoppages. If the process typically needs adjusting every three hours, sample a pair about every 30 minutes. Some texts state a different interval. Follow your course material for the exam.

Worked example: a turned shaft

Say a lathe turns shafts with a diameter spec of 10.00 ± 0.08 mm (illustrative numbers).

  • LSL = 9.92 mm, USL = 10.08 mm
  • Tolerance = 0.16 mm
  • One quarter of the tolerance = 0.04 mm
  • PC lines = 10.00 ± 0.04 = 9.96 mm and 10.04 mm

Zones:

  • Green: 9.96 to 10.04 mm
  • Yellow: 9.92 to 9.96 mm, and 10.04 to 10.08 mm
  • Red: below 9.92 mm or above 10.08 mm

Setup. After a tool change, the operator measures parts one by one: 10.01, 10.05, 10.02, 10.00, 9.99, 10.03, 10.01.

The second part (10.05) is yellow, so the count restarts. The next five (10.02, 10.00, 9.99, 10.03, 10.01) are all green. The process is qualified.

Running. Each half hour the operator measures two consecutive shafts.

  • 9:30: 10.02, 10.03. Both green. Continue.
  • 10:00: 10.04, 10.01. The first is right on the PC line. Shop rules treat boundary values as green here. Continue. (Agree on a boundary rule in advance.)
  • 10:30: 10.05, 10.06. Both yellow, both on the high side. The tool is wearing. Adjust the offset down.
  • 11:00: 10.00, 10.01. Back in green. Continue.

Later in the shift:

  • 14:00: 9.94, 10.06. Both yellow, but on opposite sides. The process hasn’t shifted; it has spread. The operator stops and finds a loose chuck jaw.

That last case is the most useful rule in the method. A mean shift and an increase in variation need different fixes. PRE-control tells them apart with two measurements.

Print shop turnaround

PRE-control works for any measurable characteristic with a spec. A print shop promises same-day turnaround with a target of 4 hours and a limit of 8 hours. That’s a one-sided spec. Treat the 4-hour target as the best achievable value, and the usual rule puts the PC line halfway to the limit, at 6 hours.

  • Under 6 hours: green
  • 6 to 8 hours: yellow
  • Over 8 hours: red

Twice a shift, the supervisor checks the turnaround time of two consecutive jobs. Two yellows in a row triggers a quick look at the queue and staffing before customers start missing their deadline.

PRE-control vs. statistical control charts

These two tools get confused. They answer different questions.

PRE-controlShewhart control chart
Limits based onSpecification limitsProcess data (about ±3 sigma)
Question answeredIs output meeting the spec?Is the process stable?
Data needed to startNone; just the spec20 to 25 subgroups is a common guide
CalculationsNone on the floorAverages and ranges or similar
Best useShort runs, setups, capable processesUnderstanding and reducing variation

PRE-control is easy to run, but it has limits.

  • It assumes the process is capable. The method works best when process capability is good (a capability index of at least 1; some texts ask for 1.33). A process that barely fits the tolerance will trigger constant yellow and red signals.
  • It doesn’t tell you about common cause variation. It’s a go/no-go adjustment tool, not an analysis tool.
  • It can lead to over-adjustment if operators react to single yellows instead of following the rules.

For understanding the process, use a real control chart with limits from the data. For guiding setups on a capable process, PRE-control is fast and practical. Our statistical process control guide covers the Shewhart side.

Rolling PRE-control out on the floor

The rules are simple. That is the appeal. A few practical points make them stick.

  • Paint the zones on the gauge or the record sheet. A colored strip next to the readout means nobody has to remember the PC line values.
  • Write the boundary rule down. Decide whether a reading on a PC line counts as green or yellow. Then train everyone the same way.
  • Log every pair, even the greens. The log becomes cheap evidence of how often the process needs adjusting.
  • Check capability first. Run a capability study before switching to PRE-control. If the process is barely capable, fix that first.

If operators complain that they’re adjusting all the time, that’s data too. It usually means the process spread is too wide for the tolerance.

On the exam: pre-control chart questions

Villanova lists PRE-control in the Control phase material. Expect:

  • Zone setup. Given the spec limits, calculate the PC lines. They sit at one quarter of the tolerance in from each spec limit.
  • Zone proportions. Green covers the middle 50% of the tolerance. Each yellow zone covers 25%.
  • Qualification rule. Five consecutive greens before production starts.
  • Running rules. Two yellows on the same side means adjust. Two yellows on opposite sides means stop and investigate variation. Any red means stop.
  • Comparison questions. PRE-control uses spec limits. Shewhart charts use process-based control limits.

A common trap: an answer choice that sets the PC lines at ±3 sigma. That’s a control chart idea. PRE-control lines come from the tolerance.

When you’re ready, there are a few ways I can help:

First, join 12,000+ other Six Sigma professionals by subscribing to my email newsletter. A short read every Monday to start your work week off correctly. Always free.

* * *

If you’re looking to pass your Six Sigma Yellow Belt, Green Belt or Black Belt exam, I’d recommend starting with my affordable study guide:

1)→ 🟡Pass Your Six Sigma Yellow Belt: built for ASQ, IASSC and ILSSI, 1,700+ practice questions with explanations, and six full-length mock exams for your exam

2)→ 🟢Pass Your Six Sigma Green Belt: a study guide organized by the exam Body of Knowledge, 1,300+ practice questions with detailed answer explanations, and 20 full-length mock exams

3)→ ⚫Pass Your Six Sigma Black Belt: the full Black Belt Body of Knowledge, 2,200+ practice questions with detailed answer explanations, and 20 full-length mock exams

You’ve spent so much effort learning Lean Six Sigma. Why leave passing your certification exam up to chance? This comprehensive study guide offers 1,700+ exam-like questions for Yellow Belts, 1,300+ for Green Belts and 2,200+ for Black Belts with full answer walkthroughs, access to instructors, detailed study material, and more.

​ Thousands have used this system to prepare. Join them here. 

Author

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.