Business continuity planning (BCP) is how an organization prepares to keep its critical work going, or to restart it quickly, during and after a major disruption. The disruption could be a fire, a cyberattack, a supplier failure or the loss of key staff. A contingency plan is narrower. It is a prepared “if this happens, we do that” response to one specific risk. Both belong in strategic planning, so that a deployment or a project does not fall apart when something goes wrong.
ASQ’s 2022 Black Belt body of knowledge, section I.A.4, lists contingency planning and business continuity planning next to SWOT analysis as tools that strengthen strategic planning and deployment.
Four terms that get mixed up
| Term | The question it answers | Example |
|---|---|---|
| Risk mitigation | How do we make this less likely or less severe? | Qualify a second supplier for a key sensor |
| Contingency plan | If this specific risk happens, what do we do? | If the pilot line goes down, run the trial on line 2 on the night shift |
| Business continuity plan | How do we keep critical work running through a major disruption? | Take orders by phone and ship from the second warehouse while the main site is closed |
| Disaster recovery plan | How do we restore IT systems and data? | Restore the order system from last night’s backup at the standby data center |
Mitigation happens before the event. The other three are prepared before the event and used after it. A contingency plan always has a trigger: a defined event or threshold that puts the plan into action. For the full risk process, see risk analysis and mitigation.
What a contingency plan contains
- The risk it covers, in one sentence.
- The trigger: the event or the number that starts the plan.
- The actions, in order, with an owner for each.
- What must be ready in advance, such as a spare part, a signed backup contract or a trained person.
The steps of business continuity planning
- List the critical processes and what each one depends on: people, sites, systems and suppliers.
- Run a business impact analysis (BIA). For each process, estimate what downtime costs per hour or per day, and the longest outage the business can tolerate.
- Set recovery objectives. The recovery time objective (RTO) is how fast the process must be back. The recovery point objective (RPO) is how much data you can afford to lose.
- Choose strategies. Options include a second site, a backup supplier, safety stock, a manual workaround and cross-trained staff.
- Write the plan. Who declares the emergency, who calls whom, and the steps in order.
- Test it. Walk through scenarios at a table, then run drills. An untested plan is a guess.
- Keep it current. Review it once a year, and whenever a process, system or supplier changes.
ISO 22301 is the international standard for business continuity management systems.
Worked example: is the plan worth the money?
A distributor runs a business impact analysis on three processes.
| Process | Loss per hour down | Longest tolerable outage | Recovery time objective |
|---|---|---|---|
| Order entry | $6,000 | 12 hours | 8 hours |
| Shipping | $2,500 | 24 hours | 16 hours |
| Payroll | $200 | 5 days | 3 days |
Each recovery time objective is shorter than the longest tolerable outage. Order entry costs the most per hour, so it is planned first.
Today. If the order system fails, rebuilding it takes about 48 hours.
Loss = 48 × $6,000 = $288,000
With a tested continuity plan (a standby system and a paper order form for the phones), order entry is back in 8 hours.
Loss = 8 × $6,000 = $48,000
IT puts the chance of such a failure at 25% in any year.
- Expected yearly loss without the plan: 0.25 × $288,000 = $72,000
- Expected yearly loss with the plan: 0.25 × $48,000 = $12,000
- Reduction: $72,000 − $12,000 = $60,000 a year
The plan costs $40,000 a year to keep ready. On expected value it comes out $60,000 − $40,000 = $20,000 a year ahead.
Expected value is not the whole case. A 48 hour outage is four times the 12 hours the business says it can tolerate. Some customers who cannot order for two days will not come back. For events that are rare but severe, a continuity plan can be the right call even when the expected value math is thin.
The logic is the same probability times impact scoring used in risk analysis and in FMEA.
Where a Black Belt meets this
- Deployment planning. What if a champion leaves, the training budget is cut or a key system arrives late? Put contingency plans with clear triggers into the deployment plan.
- SWOT. The threats in a SWOT analysis are the starting list of scenarios to plan for.
- Improve. Lean changes can remove the buffers a continuity plan relied on. Less inventory and a single supplier are common examples. Recheck the plan when you change the process. See supply chain management.
- Pilot and Control. A pilot plan needs a fallback. The response plan in a control plan is a small contingency plan: a trigger and a prepared action.
What to expect on the exam
This is an Apply level topic. Know the purpose of business continuity planning: to keep critical operations running, or restore them quickly, during and after a disruption. It is not a way to remove all risk. Recognize a contingency plan by its two parts, a trigger and a prepared action. Know that a business impact analysis sets the priorities, and that a plan has to be tested to be trusted.
When you’re ready, there are a few ways I can help:
First, join 12,000+ other Six Sigma professionals by subscribing to my email newsletter. A short read every Monday to start your work week off correctly. Always free.
* * *
If you’re looking to pass your Six Sigma Yellow Belt, Green Belt or Black Belt exam, I’d recommend starting with my affordable study guide:
1)→ 🟡Pass Your Six Sigma Yellow Belt: built for ASQ, IASSC and ILSSI, 1,700+ practice questions with explanations, and six full-length mock exams for your exam
2)→ 🟢Pass Your Six Sigma Green Belt: a study guide organized by the exam Body of Knowledge, 1,300+ practice questions with detailed answer explanations, and 20 full-length mock exams
3)→ ⚫Pass Your Six Sigma Black Belt: the full Black Belt Body of Knowledge, 2,200+ practice questions with detailed answer explanations, and 20 full-length mock exams
You’ve spent so much effort learning Lean Six Sigma. Why leave passing your certification exam up to chance? This comprehensive study guide offers 1,700+ exam-like questions for Yellow Belts, 1,300+ for Green Belts and 2,200+ for Black Belts with full answer walkthroughs, access to instructors, detailed study material, and more.
Thousands have used this system to prepare. Join them here.