Hello all,
I taking now the the green belt course and I am reallz suks in math.
So I do study alot and make alot of practicces
So I do have some questions such as this one:
A shoe manufacturing firm learned through a Lean Six Sigma project their boot soles
could be made of a different material requiring two less steps in the process. Removal
of these two steps yielded a monthly cost savings of $7,500. Therefore the reported
financial savings for this LSS project were _____________.
a. $45,000
b. $75,000
c. $90,000
d. $120,000
The answer was C.
I do not know how the answer is 90.000
I would appreciate if u can help me
Thx alot