  • in reply to: Six Sigma Certification Questions #5943
    reham elmahdy
    Participant

    Basic Green Belt Study Guide (Free)

    Does anyone know the solution for this:

    Availability: 8 hours were available but it only ran 6 hours
    Performance: 300 units were produced
    Quality: Of 300 items produced, 30 were defective
    OEE is 40.5%
    How many items should this process have produced in the available time?